Home | Design Notes | Deck | Preliminary Design
 In selecting the correct
bridge type it is necessary to find a structure that will perform its required
function and present an acceptable appearance at the least cost.
Decisions taken at preliminary design stage will influence the extent to
which the actual structure approximates to the ideal, but so will decisions
taken at detailed design stage. Consideration of each of the ideal characteristics
in turn will give some indication of the importance of preliminary bridge
design.
Constraints
The construction depth available should be evaluated.
The economic implications
of raising or lowering any approach embankments should then be considered.
By lowering the embankments the cost of the earthworks may be reduced, but
the resulting reduction in the construction depth may cause the deck to
be more expensive.
Headroom requirements have to be maintained below the deck; the minimum
standards for UK Highway bridges are given in TD 27 of the Design Manual
for Roads and Bridges.
If the bridge is to cross a road that is on a curve, then the width of the
opening may have to be increased to provide an adequate site line for vehicles
on the curved road.
It is important to determine the condition of the bridge site by carrying
out a comprehensive site investigation. BS 5930: Code of Practice for Site
Investigations includes such topics as:
Selection of Bridge Type
The following table is intended to be a rough guide to the useful span ranges of various types of deck.
Span
Deck Type
 
Up to 20m
 
Insitu reinforced concrete.
Insitu prestressed post-tensioned concrete.
Prestressed pre-tensioned inverted T beams with insitu fill.
 
 
16m to 30m
 
 
 
Insitu
reinforced concrete voided slab.
Insitu prestressed post-tensioned concrete voided slab.
Prestressed pre-tensioned M and I beams with insitu slab.
Prestressed pre-tensioned box beams with insitu topping.
Prestressed post-tensioned beams with insitu slab.
Steel beams with insitu slab.
 
30m to 40m
 
 
Prestressed
pre-tensioned SY beams with insitu slab.
Prestressed pre-tensioned box beams with insitu topping.
Prestressed post-tensioned beams with insitu slab.
Steel beams with insitu slab.
 
30m to 250m
 
 
Box
girder bridges - As the span increases the construction tends to go
from 'all concrete' to 'steel box / concrete deck' to 'all steel'.
Truss bridges - for spans up to 50m they are generally less economic than plate girders.
150m to 350m
Cable stayed bridges.
350m to ?
Suspension bridges.
Preliminary Design Considerations
Costing and Final Selection
The preliminary design process will produce several apparently viable schemes. The procedure from this point is to:
The final selection will be based on cost and aesthetics. This method of costing assumes that the scheme with the minimum volume will be the cheapest, and will be true if the structure is not particularly unusual

Design Standards | Bridge Components | Choice of Deck